Project DirectoryProject sitesTeachers



Home

The Project Launch

The Preparation

The Background

The Workshop Construction Phase

Press Items

First Tesserae Laid

Progress as at 1st December 2005

Progress Pictures - as at December 20

Stanway Roman Doctor's Grave

Progress as at 23 January 2006

Progress as at 23 February 2006

15 March - 8 characters completed

Companion mosaics are grouted

Progress as at 22 April 2006

Last tile laid on the first half - 5 May

Operation Lift & Shift - 10 May

Open Days

Progress as at 2 June 2006

Progress at 19 June 2006 & Anne Schwegmann-Fielding's Roman Watering Can

Progress as at 12 July 2006

Second half almost finished!!


A view of the mosaic from the starting gate end © Peter Herring
A view of the mosaic from the knot end © Peter Herring
Open Day workers - not time to look at the camera! © Peter Herring
Happy open day workers © Peter Herring
Happy Open Day workers © Peter Herring
Happy mosaic family © Peter Herring



   
   

Progress as at 2 June 2006
Location: Essex

With only 3 weeks work, we have made a tremendous start on the second half of the Mosaic.

Over the half term week the mosaic workshop was open to general public volunteers for four days. This has enabled us to get off to a cracking start on the second half - many thanks to all involved.






 



Legal Notice | Site by Torchbox

© Countryside Agency 2006